Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline

4 replies [Last post]
Patrick Osakwe
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 19 Sep 2012
Posts: 17
Groups: None
Hi everyone! What happens when you take a snapshot (baseline) of current update but the dates differ when you assign it as the primary baseline. The dates are different when you add BL1 start and finish column for comparison. Has anyone experienced this before? Can you guys help please? Regards, Patosaks

Replies

Godwin Ifeanyi
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 29 Dec 2013
Posts: 5
Groups: None

Hi Pat,

I think the problem you are experiencing in the display of your Initial and progress baseline has to do with your set Planned  date and start date.check the date sttings,if it does not tally,it probably means that is where the problem comes from.

Godwin Ifeanyi. 

Rafael Davila
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Patrick Osakwe
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 19 Sep 2012
Posts: 17
Groups: None
Thanks Ronald and apologies if I am asking an already asked/answered question but my question is that when I maintain current update as my baseline before schedule, the dates are different from the current update before I schedule. It should be the same as it is current but differs when I assign the curent as my baseline. That's my question. Regards, Patrick
Ronald Winter
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

This question gets asked (and answered) weekly in this forum.  You are looking at the P6 Baseline PLANNED Start and PLANNED Finish dates.  Compare them against your current schedule’s Planned Start and Planned Finish dates and I suspect you will see that they match.  Good luck!