Global Change

1 reply [Last post]
Adekunle Arisilejoye
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 52

hi,

 

Please how you write a filter or global change to display activities forecasted more than 30D of the last update.

I have the last update saved as a basline.

Cheers

K

Replies

Adekunle Arisilejoye
User offline. Last seen 5 years 5 weeks ago. Offline
Joined: 3 Apr 2008
Posts: 52

Resolved. 

Variance BL finish date

 

Cheers