daily target

1 reply [Last post]
ronron martinez
User offline. Last seen 8 years 18 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Dear All

Due to project delay the client have prepare their own schedule as per the remaining work divided to duration of 14 weeks. therefore client come out the daily target however I have concern on the other activity if the activity 1 example cannot meet the daily target then other activity will also affected

is this the write method for planning. any advise

Regards
Ronron

Replies

Mike Testro
User offline. Last seen 24 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Ronron

This is unusual - unles you have been asked to prepare a recovery schedule and you have failed to issue it.

Normally the Employer cannot instruct you to work to his programme - it could be constructive acceleration and cost the Employer a lot of money.

When you get your EoT in place the problem may go away.

Best regards

Mike Testro