Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

VICO CONTROL 2009 - HOW TO INSERT COSTS IN ACTIVITIES?

1 reply [Last post]
José Otávio
User offline. Last seen 6 years 50 weeks ago. Offline
Joined: 2 Oct 2011
Posts: 8
Groups: None

Hi all,

 

Somebody would know how to insert costs in activities in Vico Control 2009?

 

Best Regards,

Be BbbesBJosé Otávio.

Replies

Forest Peterson
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 22 Mar 2011
Posts: 33

try the resource registry and add the applied resource time unit cost