Staircase Construction- RCC

1 reply [Last post]
Saju TS
User offline. Last seen 9 years 35 weeks ago. Offline
Joined: 24 Jun 2009
Posts: 22

Dear all,

When can I start Staircase work

1.Ground floor slab

2 .Columns

3 .beams

4. RCC walls

5. First Floor Slab

------------------------------

6 .Columns

7.Beams

8. RCC walls

9.Roof Slab

From where i can start  RCC staircase construction

Thanks

Replies

Mike Testro
User offline. Last seen 29 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Saju

You have to have at least two slabs to support the staircase and it can follow the structure upwards.

It depends on the construction method statement because the stairwell may be used for vertical access and hoists.

I would also consider a precast option which can be dropped into place in one day.

Best regards

Mike Testro