Staircase Construction- RCC

S
Saju TS 👤 Member for 16 years 11 months

Dear all,

When can I start Staircase work

1.Ground floor slab

2 .Columns

3 .beams

4. RCC walls

5. First Floor Slab

------------------------------

6 .Columns

7.Beams

8. RCC walls

9.Roof Slab

From where i can start  RCC staircase construction

Thanks

M
Mike Testro 👤 Member for 20 years 5 months

Hi Saju

You have to have at least two slabs to support the staircase and it can follow the structure upwards.

It depends on the construction method statement because the stairwell may be used for vertical access and hoists.

I would also consider a precast option which can be dropped into place in one day.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts