Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Steep Staircase

8 replies [Last post]
moutaz aldeib
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
I have read a paper, in that paper I read this expression which I could not understand it well, it’s "Steep Staircase Schedule".

Replies

Hashim Muhammud
User offline. Last seen 13 years 16 hours ago. Offline
Joined: 7 Mar 2004
Posts: 38
Groups: None
Hi Francis,

I think you misunderstood what i meant... yes, I was speaking about the manpower required for the project at the different phases of the project... not with the different types of works... so, when you compare between a particular kind of internal finish and the structural work, you are right... but here we are speaking about the steep staircase, which is something about the overall project... and Clive is again right, because that is the time (see the comment), when it is going to have the highest manpower in the project...

Finally, I don’t say that steep staircase schedules are a must or 100% right in the building construction industry... but, what i want to say is that, they are likely to be seen in this industry...

Cheers,
Hashim
Clive Randall
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
For a high rise building I would anticipate that the third and the first part of the fourth quarter would result in the highest level of manpower on site. This is due to the frame still being under construction while the lower floors are being fitted out.
On this basis I do not understand your assumptions and would be interested to see your manpower s curve that shows greater manpower during the structural works.
Francis Moyalan, ...
User offline. Last seen 6 years 6 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 105
Groups: None
Hashim,

What I have seen in the actual scenario for high rise buildings .... the structural prortion requires more manpower and resanobaly lessor duration, where as towards the end of the project where internal finishes will be in full swing, the duration required will be much more even if the manpower anticipated for individual trades is less, and hence they can be overlapped ( happen simultaneous) to make a sensible schedule which generates a uniform S curve...and unlike what you stated where, internal fnishes consumes more manpower(yes, ofcourse- overlapping makes excess manpower, and structural portion lessor manpower...),

Thanx,

Francis
Hashim Muhammud
User offline. Last seen 13 years 16 hours ago. Offline
Joined: 7 Mar 2004
Posts: 38
Groups: None
hi,

I also stand with Clive. because, as he said in building works the last half or one third is the time, in which most of the finishing activities are going to work. this is because the duration of this activities are much lesser than the duration we need for core civil works. So, it is common to have them overlapped.

hashim ;-)
Clive Randall
User offline. Last seen 17 years 27 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Not sure I would totally accept this explanation as being a failure of a programme. In building in a single activity such as frame construction I would expect less activities when interior finishes commence the number of trades increase and so does the number of activities it therefore stands to reason that the end of the programme may well have more activities occuring at the same time as the begining
Clive
Dana Qandah
User offline. Last seen 15 years 48 weeks ago. Offline
Joined: 8 Aug 2006
Posts: 43
Groups: None
Moutaz,

it will be good if they are spread all over the schedule, anyway i knew this expression "steep staircase" just recently but what i think its a negative term.

Dana
moutaz aldeib
User offline. Last seen 3 years 35 weeks ago. Offline
Joined: 31 Dec 2003
Posts: 291
Groups: None
Dear Dana,

Thanks a lot for your explanation, I now understand well what it means Steep Staircase.

But if the manpower is enough, I think shcedule the activities to be done at the same time is good to crash the schedule.

Best Regards,

Moutaz
Dana Qandah
User offline. Last seen 15 years 48 weeks ago. Offline
Joined: 8 Aug 2006
Posts: 43
Groups: None
Check out this site:

http://www.pinnacleone.com/e-newsletter/wwmpf/2005_01.html

and in particular this:

Is the Contractor’s Schedule a "Steep Staircase" Schedule?

Does the Contractor’s schedule show a large number of work activities scheduled to be done at the same time? In particular, look out for "stacking" during the last half or third of the project time frame. This may indicate an unbalanced schedule with too much time provided for the structure and building shell and not enough time for interior finish work and completion activities, such as start-up and commissioning. A steep staircase schedule may also result from inadequate consideration of manpower when work activities slip on projects with delays. This is sometimes referred to as "schedule compression."

On most projects, a well planned schedule, whether it is a baseline schedule or a schedule update, will have an even distribution of activity bars in time rather than a steep staircase of work activities. Too many activities shown going on at the same time is usually not realistic and schedules like these are often not achievable. To assess this situation, think about the manpower or number of crews that would be required to start and finish 25 or 30 activities (or more) in a month, and think about the manpower likely to be provided by the subcontractors. Will there be adequate manpower?