Hi Guys,
I’m just posting to see if anyone can help with a query I have on productivity.
I work on an oil refinery for a large E&I contractor who hold the term contract here. Our duties are to perform all project works from installing new cables for substations to piping up new instruments. This means my programme is made up of hundreds of jobs that range from 6 hours up to 5000 hours.
A senior member of staff has asked me to take a look at recording productivity for each job. I am able to record burned hours through a clocking system and we record which job each guy on site has been working on daily. We can effectively whittle the overall burned hours down to each job number from this. We also receive an estimate of each job so I can populate the budgeted hours into the programme. So as the percentage rises within the programme (% is linked to hours earned), we would just use the equation:
Hours Earned (% of estimate complete) over Hours Burned (Collected from clocking system)
An example is:
Hours Earned = (50% of works complete on 1000 hour estimate) = 500 hours
Hours Burned = Straight from clocking system = 600
Productivity = 500 over 600 which would give me 0.833...
My problem lies when we get site instructions through. We don’t receive estimates for these so the labour units and durations are unknown. If I was to use the same example:
Hours Earned (50% of works complete on 1000 hour estimate) = 500 hours
Hours Burned = Straight from clocking system = 600
This would produce the same productivity as above - 0.833...
BUT if we had completed 50% of a 1000 hour SI linked to the same job it should be as follows:
Hours earned = 500 hours from estimate (50% of 1000 hours) + 500 hours from SI (also 50% of 1000 hours)
This would then be 1000 hours over 600 hours which would show our productivity to be 1.66...
The problem lies in not knowing any information about our SI’s.
Any guidance would be greatly appreciated!
Kind Regards,
David Craig
Replies