Histograms and S Curves

5 replies [Last post]
Sabrina Price
User offline. Last seen 12 years 11 weeks ago. Offline
Joined: 1 Feb 2012
Posts: 2
Groups: None

Hi Guys,

I'm new to planning and was wondering if you could help me. How can I extract Manpower Histograms and S Curves from a P6 Schedule.

Thanks

Sabrina

Replies

Hlamalani Baloyi
User offline. Last seen 11 years 42 weeks ago. Offline
Joined: 20 Jan 2012
Posts: 18
Groups: None

Hi Raymund,

You are all special to me, trust me.

I wanted to send her my final spreadsheet so she can check the formulas from there, it will be really difficult for me to explain the formulas on the spreadsheet.

Otherwise i will send everyone the steps in terms of importing information from P6 and exporting it to Excel,

 

Thnx guys

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi Hlamani,

Why don't you just post the steps so that others may be shared with your good solution...

Sabrina is as special as others too...

 

Thanks,

Hlamalani Baloyi
User offline. Last seen 11 years 42 weeks ago. Offline
Joined: 20 Jan 2012
Posts: 18
Groups: None

Hi Sabrina,

I am also new on P6,

I have just printed my Histogram and S-curve for the 1st time, its easy but you need to know the steps, you can e-mail me: balobros@gmail.com

Rafael Davila
User offline. Last seen 13 hours 27 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Jose Frade
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None

Hi Sabrina,

 

Best way is to export the manpower to excel (totals by period you need - week, month, etc) and then do them in Excell.

 

Other option is to use Ressource Usage profile and Spreadsheet  on top icon bar menu.

Hope it helps

 

BR

 

JMFrade