Generating S-Curve and Histogram

1 reply [Last post]
Ese Osoro
User offline. Last seen 12 years 42 weeks ago. Offline
Joined: 3 Mar 2008
Posts: 6
Groups: None
Hi All,
I did carry out steps to generate S-Curve but seems not to work. While carrying out the steps , there seems to be no histogram on the activity usage profile. Do i have to generate the histogram first before applying the steps to generate the S-Curve. let me know hwo to generate the histogram.
Thanks for the urgent assistance
Regards
Ese

Replies

Ali Farhat
User offline. Last seen 13 years 42 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
I dont know what are the steps you followed but please consider the following notes:
right click on the graph in the right bottom corner -> activity usage profile options, data tab:
-show bars/curves -> check the box under "by date" for histogram, and under "cumulative" for curves

-choose the "costs" in the display section

-make sure the to choose the total in the "filter for bars" section

if still not working, please tell me what steps are you following.