Hi all planners,
I am Evaluating Risks and also the impacts on Cost and Schedule dates of the Projects (for the first Time) ,Following are the issues that i have faced till now,
1- i have entered a risk,its impact date, WBS to which risk applies, and impacted Labor,Nonlabor units and expenses.but when ever i Calculate the impact,inly impact on cost is shown and no impact on schedule is calculated.i wonder if there is some step I am missing.
For example,
Risk Type: Rainy Season
Effected Date: 01-12-2011
Effected Labor units: 30
Other expense: $5000.
Risk Priority: Top
Now when I calculate the Impact it only shows the impact on ost.But logically when Working units (days) are delayed (Non work), then I should also Change the schedule dates and show the schedule impact also.yes I know that one way is to creat a calender of non work days,but this is just an example to clarify my query.
2-suppose that the Risk is applied to a certain activity.i have not found any option that can be used for this purpose.Because when you apply it to WBS,primavera P6 performs top down estimation for all activities in the specified WBS.
Any expert advice shall be highly appriciate.
best Regards.
Replies