Resource: Total Manpower

1 reply [Last post]
Muhammad Aqeel
User offline. Last seen 13 years 9 weeks ago. Offline
Joined: 18 Apr 2009
Posts: 30
Groups: None

Dear All,

 

Please some can help me find out the soluation after the cost loading in P6 how can i Manpower load thru Excel or Gobal Change  how can i get number of Manpoers  (for example):  activity is Fininshing work

COst is 100000SR

Rate is 5.00

Mandays are 24000

No. of manpower are 240

 

thanks lot

maqeel2008@hotmail.com

 

Replies

Rashid Iqbal
User offline. Last seen 12 years 30 weeks ago. Offline
Joined: 8 Apr 2009
Posts: 16

 

Aqeel,

Manpower has to be loaded in form of the Budgeted Hrs. There are ways to do an import from Excel....you can give it a try. First export the data related to Activties, Reosurces and Resource Assignments, eidt the excel file for the budget hrs and then import it back.

 