Bridge Construction Schedule

1 reply [Last post]
abdallah riad
User offline. Last seen 12 years 15 weeks ago. Offline
Joined: 20 Feb 2004
Posts: 23
Groups: None
Hi,

kindly provide me with Bridge Construction Schedule in prx format.

Regards,

Replies

Samer Zawaydeh
User offline. Last seen 6 years 16 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Abdallah,

It is better to create your own depending on the type of bridge that you have. Basically, you will have the following sections:

1. Material Submittals.
2. Shop drawings.
3. Procurement
4. Construction
I. Excavation

II. Substructure
a.Blinding
b.shuttering
c.Reinforcement/ concreting
d.Deshuttering
e.Concrete protection.
f.Backfil

III. Superstructure
a.shuttering
b.Reinforcement/ concreting
c.Deshuttering
d.Surface protection (paint, if any)

IV. Deck
a.shuttering
b.Reinforcement
c.EM services installation
d.concreting
e.Deshuttering

V. Wearing surface
a.asphating
d.demarcation paint
c.signage
d.electrical works
e.mechanical works

I hope that the general information above will help. If you have a specific question, please let us know.

Samer