Planning Department Duties

7 replies [Last post]
hadi mahmoodvand
User offline. Last seen 12 weeks 5 days ago. Offline
Joined: 6 Oct 2008
Posts: 10
I just want to know what is the Role And duties of a planning offince since they decide to participate in a project tender with their proposal till to Deliver all project’s deliverables.
Thanks

Replies

hadi mahmoodvand
User offline. Last seen 12 weeks 5 days ago. Offline
Joined: 6 Oct 2008
Posts: 10
Dear Ferdinand
Dear Samer
Sorry for being too late and thanks a lot for your constructive explanations.
Good luck
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Hadi,

The difference between the Tendering Stage and the Construction stage is huge.

Plenty of information available online to describe the Planning activities from A-Z during the Construction stage.

Let us know if you have any specific questions.

Good luck,

Samer
Ferdinand Fincale...
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 2 Aug 2008
Posts: 140
Hello Hadi,

To name a few planning duties after you completed the stage of gathering informations, programming schedules, loading resources, and setting up baselines, the next step is on the updating and monitoring of actual work deliveries as per you planned aspects may it be an engineering drawings supply, client’s deliverables, and project supplies such as manpower, material and equipment. It is then more on project management as the project progresses. That also includes risk assessment, time impact analysis on matters of additional works and variations. In your progress monitoring and updating, there would often be re-scheduling of delayed activities that affects the entire program and its completion. Weel, it simply is not limited to updating and monitoring, but the planner has got to disseminate the information to all concerned as to the vital statistics of the project, its recovery recommendation on cases of delayed works, and further enhancement of work for earlier delivery. Contruction methodologies also needs to be reviewed in support to the construction section in its work execution enhancement.

Planning is from project conception until its completion. Try to research for more. There are some white paper in the Planning Engineers Organisation website that you can download as reference.

Just sharing.

Best regards,
Ferdinand
hadi mahmoodvand
User offline. Last seen 12 weeks 5 days ago. Offline
Joined: 6 Oct 2008
Posts: 10
Dear Samer
My question was general. actually i mean the tasks which should be done by planning team in every stages of project and disciplines. assume the project is under construction.what should do the involved persons in planning office in detail(scheduling eng.,cost eng.,...).
Thanks.
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Hadi,

If you are still at the stage before project initiation, then the most important issue is the Risk Identification and Management. A good source would be the PMBOK, they have a process for Risk Management. If you specify the project type maybe we can assist in identifying few items that you and your team would want to consider.

Developing a Schedule to meet the project duration is a challenge.

Good luck,

Samer
hadi mahmoodvand
User offline. Last seen 12 weeks 5 days ago. Offline
Joined: 6 Oct 2008
Posts: 10
Dear Samer
Thank you for your explanations.but it’s up to bid participation.assume you’ve been accepted to implement the project.what are the sequential functions?
would you please offer some useful sources.
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Hadi,

The planning department need to develop a Schedule based on the information that they have to show that the Project can be delivered within the Contract duration.

This will include reviewing all the Tender documents; Contract Conditions, Specification, plans, BOQs and any information that you obtain after the site visit.

After studying all the information, you will develop a risk matrix associated with the project, and add the necessary time for uncertainties in your tender schedule. The productivity rates and resources will be based on your previous experience, project location, and your team estimates.

Please remember that this is a team effort and not a functional department output. The planning department must engage all shareholders on the team and use their input to build the Tender Schedule.

Subsequently, your top management will review the plan and take the necessary action to bid or not to bid.

Good luck,

Samer