Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

High rise building schedule

3 replies [Last post]
Aktham ABOU ELNIAAJ
User offline. Last seen 16 years 37 weeks ago. Offline
Joined: 29 Apr 2006
Posts: 13
Groups: None
Hello all planners,
I have my experience in Oil and Gas Industries I have been assigned as a planner for high rise building (over 50 floors), appreciate if any can give me some key points to look for when building the schedule.
Also knowing the area of the building and the cycle for each floor (which is 6 days for each floor) how can I calculate the number of tower cranes and stationary concrete pumps required to meet the target dates?

Replies

Clive Randall
User offline. Last seen 17 years 21 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
High rise has a number of constraints

These can be broken down into several key factors

1) foundations and substructure
2) superstructure
3) Cladding
4) fitting out
5) handover cycle

You at the moment appear to be focussing on the structure and particuarly say cranes and pumps.

Looking at cranes first what Andrew says is pretty much there but I would add another couple of factors.
1) what the vertical elemnt formwork looks like. In the case of cores is it self climbing and in the case of columns where are they stored and erected this all requires crane time
2) the possible locations for cranes will they self climb within the building or will they be fixed to the external elevation, there will be a limit on how many you can locate on site.
3) whatever you do I would recomend that you have complete floor plate coverage with your cranes to minimise cycle times.

On the pumping side you need to start with access to the discharge point for vehicles. No point having 10 pumps if you cant feed them. Topside you should look at placing booms which can be located where they will be required. Also you need to look at how you place concrete in the verical elemnts if you can do it with pumps that releives the crane.

Finally look at how you move your formwork, will you have a formwork hoist, or tables or tradditional it will all add onto the crane requirement if you are not carefull.

Cycle times can often be determined by the logistic support facilities but also there is a limit due to the structure and curing timethis helps.

By the way we get down to 4 day cycles here in HK or below and I did a job in Abu Dhabi in the mid 80s where we were down to 2 plus


Andrew Pearce
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 11 Jun 2001
Posts: 175
Requirement for concrete pumps is derived from quantity of concrete to be placed divided by out put from pump.

Requirement for tower cranes is similar, calculate number of lifts required (number of table forms, bundles of rebar etc) make an estimate of how many lifts can be made in a day.

Divide total number of lifts per day by number of lifts per crane = number of cranes required. Note at some stage you need to make allowance for crane downtime due to maintenance and high winds,
Mohammed Shafiq
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 13 Feb 2007
Posts: 13
Groups: None
Who are you working for?

I have worked in Dubai and Abu Dhabi.

I too would be interested to know the answer to your question. Never planned a high rise building before.

What’s it like planning for the oil & gas sector? What jobs have you worked on in the oil & gas industry?