Why my Percentage of completion is so low?
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Percentage complete at summary levels only works correct for money. (Primavera enterprise) because money is the only part what can be added. so Check if every activity has a cost budget. it can be from units (units x rate) or else. Check also if youve a budget (cost) at completion and check the earned value (cost). also check your actual and remaining costs. If these values are correct on activity detail your % complete on summary level should be correct.
kind regards
Henk
Hi,
Please, investigate the parameters of the 58% and 53%, maybe 58% is based on resources as you said but the 53% is based on total duration or cost. We need to compare two things in the same case means apple to apple not orange to apple.
best regards
Hi,
Check Summary bar "opition" !
Whether it is Duration, Resource or Cost ?
Cheers
Hi Juan
Did you checked the resource curve projection? is it linear?