Resource Computation

3 replies [Last post]
Shahzad Munawar
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
In a road project, after assigning each equipment to each activity, it is obevered that P3 calacultes the total no of equipment without taking into account overlaping period.

e.g.
1) One Loader is assigned to Improved Subgrade from 20/9/03 to 10/10/3 and
same Loader is assigned to granular sub base from 11/10/3 to 15/11/3

2)One Loader is assigned to Improved Subgrade from 20/9/03 to 10/10/3 for Section 1 and
same Loader is assigned to Improved Subgrade from 11/10/3 to 15/11/3 for Section 2 in the same schedule

when i calculate no of dumpers for the above two cases, it comes out as 2 dumpers instead of one for above subject cases and P3 should calculate one dumper only for the entire period whereas it calculates two dumpers? why



Replies

Morteza Jafari
User offline. Last seen 11 years 40 weeks ago. Offline
Joined: 20 Jul 2003
Posts: 33
Hi sir
May, I can help you, I think you have limited resouce and you want to know how we can this resource for activities, you should do leveling for your resources, you can select "Tools" and then "level" next go in tab of resource. just you shall know leveling to make a new schedule based on logical relationship of activities.
I hope the above is clear.
Shahzad Munawar
User offline. Last seen 8 years 50 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Our requirement is only to use one loader for these two activties then how we assign loader for these two activites so that net result should come out as one loader?
Forum Guest
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
It is because of the same dumper assigned to work on the same duration for two concurrent activities, so P3 calculates 2 dumpers.