Reading monthly Original budget hours

2 replies [Last post]
Sanjay Nair
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 21 Jul 2006
Posts: 8
Groups: None
Hello,

Is it possible to read the monthly Original budget hours or spent hours or ETC for each resource grouped by activity directly through database? If yes, then which are the tables to use?

It will be of great help.



Thanks & regards,

Sanjay Nair

Replies

Sanjay Nair
User offline. Last seen 16 years 39 weeks ago. Offline
Joined: 21 Jul 2006
Posts: 8
Groups: None
Hi Dieter,

Yes, the software is P3ec. I will check the documentation.
Thanks.


Regards,
Sanjay
Dieter Wambach
User offline. Last seen 6 years 52 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Sanjay
response is a little difficult without knowing the software you use. You speak of a database, so I assume P3e/p5:
One of the P3e-CDs is documentation. There you’ll find
Documentation\Technical Documentation\Schema Docs\PM50SchemaDiagram.pdf
Now you can use SQL. Easier will be an access via the API.
Hope, this will help.

Regards
Dieter