Critical Path issue

No replies
Abbas Rajabpour
User offline. Last seen 7 weeks 4 days ago. Offline
Joined: 7 Oct 2022
Posts: 22
Groups: None

Hi everyone, in one of the projects this issue came up and we have two critical activities at the same time and the more important issue is the following critical activities are followed by the shorter one.

How is that even possible? 

What do I need to change?

8301
screen_shot_2022-12-15_at_8.40.16_am.png


8300
screen_shot_2022-12-15_at_8.33.48_am.png

wysiwyg_imageupload::

Rodney Jones
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

Hi Abbas,

 

Firstly, your settings show the CP defined as Total Float as Less than or Equal to Zero, and in your screen snip it shows the shorter activity having dependencies, so all those activities have Less than or Equal to Zero Total Float, the longer activity is not driving them and the longer activity also has Less than or Equal to Zero Total Float so the schedule is reporting correctly.

What you might want to look at is where the -75 days float is being generated which is attached to the longer activitiy. Check for Constraints along that longer activity dependency network.

Rodney Jones
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

Hi Abbas,

 

Firstly, your settings show the CP defined as Total Float as Less than or Equal to Zero, and in your screen snip it shows the shorter activity having dependencies, so all those activities have Less than or Equal to Zero Total Float, the longer activity is not driving them and the longer activity also has Less than or Equal to Zero Total Float so the schedule is reporting correctly.

What you might want to look at is where the -75 days float is being generated which is attached to the longer activitiy. Check for Constraints along that longer activity dependency network.

Rodney Jones
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

Hi Abbas,

 

Firstly, your settings show the CP defined as Total Float as Less than or Equal to Zero, and in your screen snip it shows the shorter activity having dependencies, so all those activities have Less than or Equal to Zero Total Float, the longer activity is not driving them and the longer activity also has Less than or Equal to Zero Total Float so the schedule is reporting correctly.

What you might want to look at is where the -75 days float is being generated which is attached to the longer activitiy. Check for Constraints along that longer activity dependency network.

Abbas Rajabpour
User offline. Last seen 7 weeks 4 days ago. Offline
Joined: 7 Oct 2022
Posts: 22
Groups: None

David, 

Thanks for your reply

Point is when we tick the " longest path", some of the other following activities which were on critical path such as

"Prepare Commissioning plan" /. "Site Access Granted". will no longer be critical but still you can see tha Kick of Meeting is on critical path


But still,  the activitiy by the name of " Delay the KOM" is still on the critical path  And as far as I know, when you have fabrication which is on critical path and have negative float of -75 and the following activitiy after that which is " delay the KOM" and that activity starts at the same time as well and it shouldn't be on critical path at all but still you can see it there.

 

8302
screen_shot_2022-12-16_at_1.23.34_pm.png

david kelly
User offline. Last seen 4 hours 3 min ago. Offline
Joined: 12 Feb 2016
Posts: 33
Groups: None

Abbas,

I am not sure I understand your question, but I will try and answer it anyway!

Tick 'Longest Path' and see if you get the result you are looking for.