Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Critical path-Longhest path

3 replies [Last post]
Rachel Dorota
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 2 Dec 2013
Posts: 16
Groups: None

Dear all,

In P6 critical activities are defined by either the total float or the longhest path. I set up a program in P6 ver7.2 and when I calculate the critical path using the Longest Path filter, the result is an empty page, meaning no activities in longest path. Why is this happening? Should I change some settings? Is it normal not to have a longest path in a project? (If it is normal how can it be justified and what does it say about the project?)

regards

 

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

One formal definition of the Critical Path is the path with the lowest total float.  That number does not need to be zero but may be more or less, depending on circumstances.  You can set a number other than zero on the Projects / Settings tab in the “Define Critical Activities” section.

I also think that you are using the wrong constraint for the end of your project.  Unless there is a penalty for early completion, then I would suggest constraining it to “Finish On or Before” a certain date.  Good luck!

Rachel Dorota
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 2 Dec 2013
Posts: 16
Groups: None

Ronald,

thanks for your advise. I removed the constraint and the longhest path appeared but as you said the overall project has float. So the critical path is not as I expected to be. In cases like that can we consider as critical activities also the activities with a float <3 to 4 days? I mean in construction projects is reasonable to make such assumption in order to be alerted?

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Rachel,

You probably do have a longest path.  I am guessing that you constrained the finish milestone with a mandatory finish constraint and that your overall project has float.  That would place your finish milestone as the sole member of the longest path.  What you are saying with the mandatory finish constraint is that the contractor is not allowed to finish early as well as late.  That would make for an interesting contract.

To understand the longest path, you need to understand the calculations behind it.  Perhaps a paper that I presented way back in 2004 called, “Longest Path Value” might be of help.  You can find this at http://www.ronwinterconsulting.com/published.htm.  Good luck!