Complex Negative Float Query

No replies
Karim Tarafdar
User offline. Last seen 1 week 3 days ago. Offline
Joined: 12 Dec 2019
Posts: 6
Groups: None

Hi all,

I am looking to resolve some negative float on a P6 schedule handed over to me.

Please note:

1. There are no hard Constraints

2. No 'Must Finish By' on the project date

3. No external relationships 

 

As you can see below, the on the 'Project Start' activity the 'Late Finish' is earlier than the 'Early Start'. (DD is July-22).

Any help would be appreciated!