Bulk New Project creation tool? or SQL function?

18 replies [Last post]
Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hello All,

 

I have recieved an excel spreadsheet that contains about 500 rows and 8 columns.

The columns are:

Project Id

Project Name

and 6 other columns that match our Project Code directory.

 

My question is, do you know of a way that this spreadsheet can be used to create new projects in bulk?

 

Regards,

 

Rod

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

guess they need a 64 bit version

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Rodel, Zoltan,

 

Thank you both for the assistance. I had to install Office 365 32 bit version to get the Parser file running. All working as described now.

 

Much Appreciated.

 

Rod

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Zoltan,

 

Tyhanks for the file but I can't get it to run either, I am using Office 365, do I need an earlier version of Excel to have this working without errors?

 

Rod

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

sent file to Rodney

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Zoltan,

 

Would you please email those parser instructions? I can't get it to run, just errors of not finding file.

 

Rod

Rodel Marasigan
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Rod,

What is the error? Is it opening the xer or loading the excel parser?

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Rodel,

 

The parser fails, the error is

and then,

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Thanks Rodel, I'll give it a try today.

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Zoltan,

 

Than picture hasn't come through properly so please email me. 

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

rodney.jones@y7mail.com 

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

rodney.jones@y7mail.com 

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

here are the instructions

not sure why so smal but if u give me your email address I can send the word file

7833
blamkcapture.jpg

Rodel Marasigan
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Rod,

The purpose of creating 2 or 3 Project in P6 is to have sample data to see or review so you can familiarize on the data that will be exported to xer and excel by xerFileParser. Once you get the idea, you can just copy and paste the project id and project description on the correct field and populate the other fields. Let me know if there is any issues.

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Rodel,

 

Great, I will download it from that link.

Just to clarify, I want to auto-create projects without having to first create them in P6. I will be bringing approx 1,000 projects in. Here is a screen snip and attached is a sample spreadsheet with only 200 rows, but you get the idea.

(Hmmm, I can't insert the spreadsheet)

Zoltan, I have not included the other 6 columns as I am not concerned about them at the moment but they are columns that are mapped to some specific Project Codes that we have created.

 

 

ProjectProject Name
P.0005151HW7 East Sprayed Sealing
P.0005293Behavioural Speed
P.0005328Facilities around schools - Reactive
P.0005352HW7 West Sprayed Sealing
P.0005353HW6 Sprayed Sealing
P.0005354HW8 Sprayed Sealing
P.0005355HW11 Sprayed Sealing
P.0005356HW12 Sprayed Sealing
P.0005357HW18 Sprayed Sealing
P.0005358HW21 Sprayed Sealing
P.0005359HW22 Sprayed Sealing
P.0005360HW27 Sprayed Sealing
P.0005382HW29 Sprayed Sealing
P.0005383MR54 Sprayed Sealing
P.0005384MR56 Sprayed Sealing
P.0005385MR61 Sprayed Sealing
P.0005386MR70 Sprayed Sealing
P.0005387MR78 Sprayed Sealing
P.0005388MR245 Sprayed Sealing
P.0005389MR253 Sprayed Sealing
P.0005390MR310 Sprayed Sealing
P.0005391MR334 Sprayed Sealing
P.0005392MR359 Sprayed Sealing
P.0005393MR377 Sprayed Sealing
P.0005394MR410 Sprayed Sealing
P.0005395MR421 Sprayed Sealing
P.0005396MR516 Sprayed Sealing
P.0005397MR558 Sprayed Sealing
P.0005398MR559 Sprayed Sealing
P.0005399Reg Roads Broken Hill WC Sprayed Sealing
P.0005401HW17 MB3 Asphalt Resheeting
P.0005412HW5 Asphalt Resheeting
P.0005413HW7 East Asphalt Resheeting
P.0005547Reg Rds Block Grant Mid Western Regional
P.0005548Reg Rds Block Grant Bathurst Regional
P.0005558BalItem 21110 Passing Lanes OW
P.0005661HW17 Mogriguy Rehab
P.0005682HW5 Kirconnel Reconstruction
P.0005800Reg Rds Block Grant Warrumbungle Ccl
P.0005856BalItem 222021 Bridge Rebuilding OW
P.0005987BalItem 22114 Concrete Pavemt Rehab OW
P.0006018BalItem 21301 Flood Mitigation OW
P.0006044HW7 B4148 LH Ford Bdge Midspan
P.0006059BalItem 21106 Sealed Road Extension OW
P.0006118HW7 East Heavy Patching Auslink
P.0006120HW7 West Heavy Patch State
P.0006210HW18 Back Creek Road Widening
P.0006276HW18 Blackmans Flat Widen & Reshape
P.0006281HW17 Marsden Rehab
P.0006406HW5 Orange Road Services Culvert Repairs
P.0006586HW17 MB2 Heavy Patch Auslink
P.0006588HW17 MB3 Heavy Patch Auslink
P.0006590HW17 North Marsden Causeways
P.0006627HW8 B9239 Unnamed Creek
P.0006677HW8 Musheroo Widening
P.0006694LGRSO MOREE Projects
P.0006695LGRSO ORANGE Projects
P.0006696LGRSO DUBBO REGIONAL Projects
P.0006698LGRSO BATHURST Projects
P.0006699LGRSO MOREE Salary
P.0006700LGRSO ORANGE Salary
P.0006701LGRSO DUBBO REGIONAL Salary
P.0006826MR633 Sprayed Sealing
P.0006827MR633 Pavement Heavy Patch State
P.0006903LGRSO BATHURST Salary
P.0006904LGRSO PARKES Projects
P.0006905LGRSO PARKES Salary
P.0006906OCCUPANT RESTRAINT
P.0006907Reactive Speed Zone Reviews
P.0006967BalItem 22201 Bridge Routine & Minor OW
P.0007113HW27 B4409 Plain Creek 22.12km NE Dubbo
P.0007161HW27 B4405 Ballimore Ck 33.84km NE Dubbo
P.0007182HW27 B4402 Spicers Ck 41.03km NE Dubbo
P.0007222B4B LR2580005 B1302 McKanes Bridge CoxsR
P.0007335HW5 B1036 Marrangaroo
P.0007421Reg Rds Block Grant Forbes Ccl
P.0007436Reg Rds Block Grant Gilgandra Ccl
P.0007463Reg Rds Block Grant Lachlan Ccl
P.0007468Reg Rds Block Grant Narromine Ccl
P.0007483Reg Rds Block Grant Parkes Ccl
P.0007488Reg Rds Block Grant Walgett Ccl
P.0007505Reg Rds Block Grant Warren Ccl
P.0007508Reg Rds Block Grant Weddin Ccl
P.0007584Reg Rds Block Grant Lithgow Ccl
P.0007591Reg Rds Block Grant Oberon Ccl
P.0007709Reg Rds Block Grant Broken Hill Ccl
P.0007734Reg Rds Block Grant Central Darling Ccl
P.0007766Reg Rds Block Grant Blayney Ccl
P.0007773Reg Rds Block Grant Bogan Ccl
P.0007776Reg Rds Block Grant Bourke Ccl
P.0007780Reg Rds Block Grant Brewarrina Ccl
P.0007803Reg Rds Block Grant Cabonne Ccl
P.0007810Reg Rds Block Grant Cobar Ccl
P.0007826Reg Rds Block Grant Coonamble Ccl
P.0007830Reg Rds Block Grant Cowra Ccl
P.0007924HW5 Meadow Flat Stabilise Orange RS
P.0008201HW12 Browns Creek Widening
P.0008245MOTORCYCLE SAFETY EDUCATION - WESTERN
P.0008300HW17 North Croppa Creek Rehab
P.0008315BalItem 22104 Flexible Pavement Patch OW
P.0008335HW17 North Gurley Foam Stabilisation
P.0008395Reg Rds Block Grant Narrabri Ccl
P.0008411Reg Rds Block Grant Moree Plains Ccl
P.0008724BalItem 22303 Slope & Retaining Wall OW
P.0008725HW28 Carnarvon Highway Rehabilitation Ca
P.0009004HW18 North Coonamble Rehab
P.0009035MR54 Perthville Rehab Bathurst Ccl
P.0009052MR253 O'Connell Rehab
P.0009122B4B LR157002 B4658 Warroo Bridge Replace
P.0009272HW17 MB2 Sprayed Sealing
P.0009274HW17 MB3 Sprayed Sealing
P.0009275HW5 Sprayed Sealing
P.0009332HW17 Mardell Cracked Reshape
P.0009444BalItem 22304 Drainage Rehabilitation OW
P.0009511HW7 B4123 Bridge Molong Ck Larriss Lea
P.0009540Reg Rds Block Grant Orange Ccl
P.0009634BalItem 22323 Slope Retain Wall Cap OW
P.0009636BalItem 22001 Routine Maintenance OW
P.0009709OLD-HW22 Waratta Ck Int Seal DONT USE!
P.0009712HW22 EightMile Ck Intl Seal Far West RMD

Rodel Marasigan
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Rod,

You can download it from the internet. There also some tutorial on how to use it. See below link.

https://cdn.planacademy.com/wp-content/uploads/2012/01/xerFileParserBuilder_2007.xlsm

The best way of doing it is by creating 2 to 3 Projects in P6 including the Project Code so you will be familiar with the data. Open all the 3 projects created (Just place holder and NO WBS , NO Activities) and export it to XER. Open the xer with the XERFileParserBuilder and fill the the project data and project code. I assumed you are familiar with P6 database field to understand the heading of the XER table. Should you have any issue, let me know. If you can share the spreadsheet, I can build the xer for you.

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

can you share the spreadsheet or a pic of it. Some fields are importable into primavera and some are not. 

Rodney Jones
User offline. Last seen 51 weeks 3 days ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hi Rodel,

 

Yes, I just want the placeholder/shell created because then I will copy my template wbs into them. What is this tool you speak of?

 

Thanks,

 

Rod

Rodel Marasigan
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Hi Rodney,

Do you mean adding those project into P6 Database without WBS and Activities?
If you are familiar with xerFileParserBuilder you can build XER with all the project in one XER and import to P6.