Bulk Removal of relationships in a programme

1 reply [Last post]
Thomas Nicholson
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 4 Oct 2006
Posts: 87
Groups: None

Morning all,

A colleague has been given a programme to use as a template for another project however she needs to remove all the logic and re-input it in the order the new project will be done. I can't seem to see an easy way to remove the logic without going through individual activities. Can anyone point me in the right direction?

Thanks in advance,

Thom

Replies

Kaif Mohsin
User offline. Last seen 6 years 35 weeks ago. Offline
Joined: 15 Feb 2011
Posts: 44
Groups: GPC Qatar

Hi Thomas,

Just copy the programme in P6 and while copying 3 different tabs will appear "Copy Project Options" then "Copy WBS Options" and finally "Copy Activity Options". Under the "Copy Activity Options", untick the Relationships Box and you will get desired result.

Best Regards,

Kaif