RESOURCES DISTRIBUTION WHEN UPDATING

1 reply [Last post]
Antonello Pumilia
User offline. Last seen 4 years 6 weeks ago. Offline
Joined: 2 Sep 2005
Posts: 3
Groups: None

Hi all,

I allocated revenues in a non labor resource assigned to activities. Now, we manually input the monthly revenues we forecast so that the curve for the remaining units (money) is not calculated by the software, maybe applying a resources curve, but it is set by ourselves according to our knowledge of what will happen.

So we have, for instance, 

    Data date   
 BudgetActualRemainingapr-21mag-21giu-21lug-21
Activity1002080535,00,040,0

Now, when I update, even by giving to apr-21 the exact number as planned (i.e.),

the precise distribution of the remaining units is messed up and recalculated, and it becomes:

    Data date   
 BudgetActualRemainingapr-21mag-21giu-21lug-21
Activity1002080525,324,525,3

How do I preserve, my original distibution?

thanks everyone that can help!

antonello

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

assign a resource curve