Creating Resource Curves for Labour Loading Profiles

2 replies [Last post]
Rodney Jones
User offline. Last seen 1 day 23 hours ago. Offline
Joined: 18 Jun 2012
Posts: 23
Groups: None

 

Hello All,

I am trying to understand how the Resource Curves are created when using the 21 points shown in the development window.

Enterprise > Resource Curves > Add or Modify.

wysiwyg_imageupload:7689:I have a 3 month duration activity with a budget spend profile of 25%, 50%, 25% but when I set the Resource Curve profile as shown, it ends up front loading all the labour in the first month.

wysiwyg_imageupload:7690:How do I make this work?

Thanks,

 

Rod

Replies

Rodney Jones
User offline. Last seen 1 day 23 hours ago. Offline
Joined: 18 Jun 2012
Posts: 23
Groups: None

Hi Zoltan, YEs, Applied at the Activity level when the Resource was assigned and then Recalced the project.

Zoltan Palffy
User offline. Last seen 2 days 14 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2890
Groups: None

Sorry I just have to ask did you assign this resource CUVREe to that activity ?