Planned curve in Resource usage profile

2 replies [Last post]
Akhtar Khan
User offline. Last seen 10 years 22 weeks ago. Offline
Joined: 3 Dec 2009
Posts: 9
Groups: None

I am using P6 Ver 7.0. Can any body tell me how to bring planned value histogram in resource uage profile.I able to get budgeted Histogram but not planned histogram.

Thanks.

Replies

PINAN T.
User offline. Last seen 5 years 44 weeks ago. Offline
Joined: 20 Jul 2007
Posts: 102

use activity usage profile

baseline tick box is there

Daniel Limson
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Akhtar,

Budgeted is the same as Plan