Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Expenses Actual Cost Based on Activity Physical%

5 replies [Last post]
troon sigma
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None

Hi,

 

I have added an expense to my activity.  Is it possible that the 'actual cost' of the expense change as physical % complete of the activity changes?

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

troon sigma
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None

Thanks a lot Zoltan

troon sigma
User offline. Last seen 2 years 42 weeks ago. Offline
Joined: 15 Apr 2020
Posts: 23
Groups: None

Thanks a lot Zoltan

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

a Global chnage will not work here

export the physcial % complete and the Expense % complete to excel

thne copy the physcial % complete to the expense complete and then import back into p6

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

a Global chnage will not work here

export the physcial % complete and the Expense % complete to excel

thne copy the physcial % complete to the expense complete and then import back into p6