Expenses Actual Cost Based on Activity Physical%

5 replies [Last post]
troon sigma
User offline. Last seen 1 week 6 days ago. Offline
Joined: 15 Apr 2020
Posts: 21
Groups: None

Hi,

 

I have added an expense to my activity.  Is it possible that the 'actual cost' of the expense change as physical % complete of the activity changes?

 

Thanks

Replies

Zoltan Palffy
User offline. Last seen 2 days 1 hour ago. Offline
Joined: 13 Jul 2009
Posts: 2891
Groups: None

glad I could help 

troon sigma
User offline. Last seen 1 week 6 days ago. Offline
Joined: 15 Apr 2020
Posts: 21
Groups: None

Thanks a lot Zoltan

troon sigma
User offline. Last seen 1 week 6 days ago. Offline
Joined: 15 Apr 2020
Posts: 21
Groups: None

Thanks a lot Zoltan

Zoltan Palffy
User offline. Last seen 2 days 1 hour ago. Offline
Joined: 13 Jul 2009
Posts: 2891
Groups: None

a Global chnage will not work here

export the physcial % complete and the Expense % complete to excel

thne copy the physcial % complete to the expense complete and then import back into p6

Zoltan Palffy
User offline. Last seen 2 days 1 hour ago. Offline
Joined: 13 Jul 2009
Posts: 2891
Groups: None

a Global chnage will not work here

export the physcial % complete and the Expense % complete to excel

thne copy the physcial % complete to the expense complete and then import back into p6