Earned value columns based on physical progress

2 replies [Last post]
troon sigma
User offline. Last seen 1 week 6 days ago. Offline
Joined: 15 Apr 2020
Posts: 21
Groups: None
Hi, My activities' % Complete Type is set to "Physical".  I enter physical progress of the activities, however the earned values do not change. If i enter duration progress e.g remaining duraiton or labor hours, the earned value change.  My question is, the earned value columns are not linked with physical progress, even if Complete Type is physical?  Thanks

Replies

Rafael Davila
User offline. Last seen 11 hours 30 min ago. Offline
Joined: 1 Mar 2004
Posts: 5010
Zoltan Palffy
User offline. Last seen 1 day 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2891
Groups: None

no they ar enot linked what you can do is creat a global chnage where the duration % complete is equal to the physical % complete.

Here is how

got to tools

global change

on the right select new

Where Physcial % is not equal to 0

Then 

Duration % Complete  =    Physical % Complete

 

on the right select Change

then on the bottom right select Commit Changes