Variance Showing in p6 even though Activity no Budget

1 reply [Last post]
Patrick Walsh
User offline. Last seen 18 hours 59 min ago. Offline
Joined: 11 Sep 2013
Posts: 5
Groups: None

hello

I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.

Please help, it has to be a setting issue i think....

Replies

Zoltan Palffy
User offline. Last seen 17 hours 53 min ago. Offline
Joined: 13 Jul 2009
Posts: 2842
Groups: None

if it has a variance it must be comparing against something do you have a baseline attached ?

see if there is an actual cost  or a cost to complete ?

if there are values here it will still show a variance

look at previous period costs