hello
I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.
Please help, it has to be a setting issue i think....
hello
I have an activity showing a cost variance in the variance column even though that activity does not have a budgeted total cost.
Please help, it has to be a setting issue i think....
Links:
[1] http://www.planningplanet.com/forums/oracle-primavera-pm6