Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Assignment

3 replies [Last post]
Chris Rymer
User offline. Last seen 26 weeks 4 days ago. Offline
Joined: 11 Jun 2010
Posts: 30
Groups: None

I am trying to change the budgeted units of a resource in the Resource Assignment spreadsheet but it is greyed out. I have another Project where I can do this but I'm struggling in the new one. Everything appears to be correctly set, such as the Duration type but unfortunately I can't amend anything. 

 

Any advice is appreciated

Replies

Zoltan Palffy
User offline. Last seen 2 hours 33 sec ago. Offline
Joined: 13 Jul 2009
Posts: 2735
Groups: None

I beleive that you are taking about actuals here ?

Chris Rymer
User offline. Last seen 26 weeks 4 days ago. Offline
Joined: 11 Jun 2010
Posts: 30
Groups: None

I have now realised that the spreadsheet is greyed out after a specific date. If I move an activity before this date, I can edit the spreadsheet, if I move it later, I can't

Chris Rymer
User offline. Last seen 26 weeks 4 days ago. Offline
Joined: 11 Jun 2010
Posts: 30
Groups: None

I have now realised that the spreadsheet is greyed out after a specific date. If I move an activity before this date, I can edit the spreadsheet, if I move it later, I can't