Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

to reverse the progress % completion

1 reply [Last post]
Umer Khan
User offline. Last seen 5 years 21 weeks ago. Offline
Joined: 19 Jul 2018
Posts: 2
Groups: None

Dear All, 

I am new user of p6 and actually i forget to make copy of base line program  and updated progress . by checking start  giving progress % and finish all activities which are complete. Now i need base line program back without progress. 

Need Help 

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

here is how to destatus a schedule 

1. copy the current schedule

2. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original

3. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.

4. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule. To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date. 

5. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.

6. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.

7. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.

8. Run the 2nd global change which sets the activity status to Not Started

1st Global Change

Subject Area: 

Activity Resource Assignments 

Where  Resource Type                  equals                    Material

 Then      Actual Material Units         =                             0 

 

2nd Global Change

Subject Area:

Activities

Where                  Activity Status                   is not equal to                  Not   Started

Then                      Activity Status                            =                                  Not Started

If this process is not used you may encounter the following error:

"Cannot set status to Not Started if activity has actuals."

 

3rd Global Change

Change duration to activities by running global change for Not Started activities

Subject Area:

 Activities

Where                  Activity Status                   is not equal to                  Not   Started

Then                      Remaining Duration               =                                    Original Duration

 

If you are recreating a schedule from an as-built schedule 1st export the actual durations to excel then import the actual durations as original durations.