Primavera Import XER

1 reply [Last post]
muhammad sajjad
User offline. Last seen 6 days 14 hours ago. Offline
Joined: 7 Dec 2019
Posts: 8
Groups: None

What happens to OBS while importing project to existing project in Primavera P6.

Replies

Zoltan Palffy
User offline. Last seen 2 days 16 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2568
Groups: None

nothing because the EXISTING project that you are updating already belongs to an OBS