Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera P6, 16.1: Progress line on collapsed group activities

2 replies [Last post]
Jon Gusto
User offline. Last seen 44 weeks 1 day ago. Offline
Joined: 2 Oct 2019
Posts: 2
Groups: None

Hi,

 

Is there any way to make progress lines track the grouping of collappsed activities. I have late start activities and it tracks the individual activities and milestones but if I collapse them in group lets say grouped in Level 1, the progress line doesnt track the delays.

 

Replies

Zoltan Palffy
User offline. Last seen 1 day 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 2740
Groups: None

no and why would you want to do that anyway ? 

Baykan Yigit Sogut
User offline. Last seen 33 weeks 3 days ago. Offline
Joined: 18 Jul 2019
Posts: 6
Groups: None

Progress line functions only in activity level. Primavera doesnot recognize the Summary bars as activity and doesnot do any plan/actual calculation.