Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera P6, 16.1: Progress line on collapsed group activities

2 replies [Last post]
Jon Gusto
User offline. Last seen 3 years 25 weeks ago. Offline
Joined: 2 Oct 2019
Posts: 2

Hi,

 

Is there any way to make progress lines track the grouping of collappsed activities. I have late start activities and it tracks the individual activities and milestones but if I collapse them in group lets say grouped in Level 1, the progress line doesnt track the delays.

 

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

no and why would you want to do that anyway ? 

Baykan Yigit Sogut
User offline. Last seen 1 year 31 weeks ago. Offline
Joined: 18 Jul 2019
Posts: 6
Groups: None

Progress line functions only in activity level. Primavera doesnot recognize the Summary bars as activity and doesnot do any plan/actual calculation.