Forum Sponsor:

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Export Cost and Resources

3 replies [Last post]
Muhammad Saqib
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Dear All,

I want to export my P6 file which is Resource and Cost loaded. I want to export the same file which includes both these data.

When i export the file by choosing project only option , the budgeted cost data is not displayed while importing this file .

 

Secondly, if i want to send the file which includes only activities and date, then how to hide the cost and resources.

 

Please explain both these methods. i would really appreciate

 

Thirdly, kindly explain the export options (project only and resource only)

 

Thanks

 

Regards,

Saqib

Replies

Muhammad Saqib
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 25 Oct 2018
Posts: 35
Groups: None

Thank You so much Alexandra.

God Bless You

Mohammad Zishan
User offline. Last seen 20 weeks 5 days ago. Offline
Joined: 2 Sep 2019
Posts: 3
Groups: None

Dear all

 

when i updating the project if i miss some thing then i want to go back few step . in Primavera P6 there are any sortcut option to go back 1,2,3 step.

 

please reply 

 

thanks

Alexandre Faulx-B...
User offline. Last seen 6 days 18 hours ago. Offline
Joined: 20 Jan 2003
Posts: 1271

Hello Muhammad,

1st question:

in the process of exporting an XER file, you will be able to edit the export template; add the necessary fields

2nd question:

it is not possible to hide cost and resources fields while exporting a project, whatever the export format is (XER, XLS, XML);

the workaround is to make a copy of your project: display the project screen, then copy and paste your project; then delete all resources and costs assignments from the project's copy; then export this file.

Alexandre