Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

HELP - Total Float While Levelling

2 replies [Last post]
Hayden Kay
User offline. Last seen 36 weeks 6 days ago. Offline
Joined: 6 Dec 2018
Posts: 3
Groups: None

Hi All,

I have a resource loaded and linked schedule with a finish milestone (forecast) linked to a constrained mandatory finish milestone(target finish date) and can see my float correctly in the Total Float column with no resource constraints applied. When i add resource levels to the schedule, it naturally extends the finish dates as i expected. My forecast finish milestone goes beyond my constrained mandatory finish milestone however my total float column has not changed and still shows a positive float! It has not calculated the REAL total float with resource levelling.

Any help on this would be massively appricated!

Cheers,

Hayden

Replies

Zoltan Palffy
User offline. Last seen 5 hours 22 min ago. Offline
Joined: 13 Jul 2009
Posts: 2377
Groups: None

glad you figured it out 

Hayden Kay
User offline. Last seen 36 weeks 6 days ago. Offline
Joined: 6 Dec 2018
Posts: 3
Groups: None

SOLVED - Use the 'remaining float' column