Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Display total float on Project level

1 reply [Last post]
Ahmed KHR
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

Dear Primavera Experts,

 My question is, How can I display the total float on the Project summary level?

The project completion milestone delayed 68 days (TF=-68), But on the project level it shown (TF=0), how can I display on this level the same TF whatever it's negative?

Please view the picture below.

NB.I use P6 R8.3

Thank you for your help in advance.

 

1856
tf.jpg

Replies

Ahmed KHR
User offline. Last seen 6 years 10 weeks ago. Offline
Joined: 10 Nov 2010
Posts: 65

I get it, I must add Must finish date to project to get this TF.