Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Overall % Complete

1 reply [Last post]
Michael Covington
User offline. Last seen 5 years 34 weeks ago. Offline
Joined: 23 Aug 2018
Posts: 2
Groups: None

If my schedule is set to fixed units, how do I get it to show a overall percent complete?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

make sure that the units columns are displayed the group and sort and select show grand totals