xer reader using PowerBI

1 reply [Last post]
mimoune djouallah
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

Guys

 

I am sharing a new PowerBI application, it reads xer file and show some information

 

WBS

Float

Predecessors and driving relationship

 

You need to install PowerBi desktop, which is a free application, please let me know if it works for you, and what kind of data you want to see.

 

https://datamonkeysite.com/2018/06/17/rewriting-xer-reader-using-powerbi/

 

Cheers

Mim

 

Replies

mimoune djouallah
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

now, when you load two XER you can compare the float and the activity description

 

https://datamonkeysite.com/2018/06/23/float-erosion-report-between-two-xer/