Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera 6 ver17.**

5 replies [Last post]
Ruel Camaquin
User offline. Last seen 28 weeks 4 days ago. Offline
Joined: 16 Nov 2008
Posts: 94

Hello Guys,

Just like to know if some of you guys experience what we experience with the latest version of P6.

We migrated from v8.4 to v17.12.2 and everything has been okay, but when we import our native .xer file and send it to a client with same version, once opened the labor and materials resources and some cost on the project went missing. We have tried this on differernet PC, different p6 project files and other clients just to check, but the end result is just the same.

And is it just us, or others also experience the same.

Hoping someone can tell us the problem or solution/work-around that we can use. Oracle has been slow in responding to our ticket request.

 

Cheers!

Ruel

 

Replies

Zoltan Palffy
User offline. Last seen 11 hours 22 min ago. Offline
Joined: 13 Jul 2009
Posts: 2287
Groups: None

to check this setting go to the projects directory

make sure that your project is highlighted

click on the resource tab 

lower right make sure that under Resource agssignments that 

Resourcces can be assigned ot the same activity more than once is NOT checked

Steven Auld
User offline. Last seen 1 day 2 hours ago. Offline
Joined: 13 Sep 2017
Posts: 105

Agree with Zoltan - It may be that there are duplicate resources against the same activity.

Primavera does not like importing the same resource against 1 activity, as it see's the resource already in the database then updates the existing value with the new value being imported.

It is looking for the Activity ID & Resource ID during import, where it see's a match it will update.

When importing, try changing the settings on the XER Import under "Activity Resource Assignments" to "Insert New".

Do not import this as an update to the existing project, as the original resource may be duplicated where there is no duplicate in the import file.

If regularly sending XER files to others for import, on the project settings disable the setting that allows Resources to be allocated to activities more than once - I'm sure that Zoltan has already put a post out with where this setting is.

Regards,

Steven

Zoltan Palffy
User offline. Last seen 11 hours 22 min ago. Offline
Joined: 13 Jul 2009
Posts: 2287
Groups: None

during the import process make sure that you modify the import configuration and under Data Type:Global make sure that under resources that under the action item that insert new is checked.

Ruel Camaquin
User offline. Last seen 28 weeks 4 days ago. Offline
Joined: 16 Nov 2008
Posts: 94

Hi Zoltan,

Again It been awhile. 

No we did not do anything with the file; it is that when export using P6 17.++ some data (resources) went missing after it is opened by the receiving end also using the same version. But not all, that makes us wonder why is the new version doing that.

Our old version is 8.4 and do not havr any issues on it...

 

Ruel

 

Zoltan Palffy
User offline. Last seen 11 hours 22 min ago. Offline
Joined: 13 Jul 2009
Posts: 2287
Groups: None

check your resources and make sure that calculate cost from unist is NOT checked if it is run a global change to change it to no.