Good Evening
I use P6V8. The schedule I inherited has activties using "physical % complete" as most common way to status progress. So are milestones.
As "activity percent complete based on activity steps" is checked at the project level, whenever I claim finish milestone, physical % complete shows 0% complete instead of 100%. This misleds foreman/engineers reading the schedule report who think planners missed to claim actual.
The only work around i found is adding a step to milestone and claiming it 100% inorder to reflect 100% under physical % complete. This solution would have worked on a small project but with milestones running in 1000s it is not a feasible option.
Hence Want to check with fellow planner on what % complete type you set milestones to, while statusing other activities with steps which are set to "physical %" type.
TIA