Adding Resources & zeroing values

1 reply [Last post]
Luke Barford
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 5 Jul 2016
Posts: 4
Groups: None

HI,

 

I having an issue when i add a new resource on to a activity, Primavera  zeroes all costs added on all previously added resource.

and re calculate the units. I hacve unticked the auto compute and calc costs from units for the resouce but still happens,

Any ideas how to stop that from happening?

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

2 things to check 

1. make sure that the duration TYPE is set to fixed duration & units/time 

you might have to add the column for duration type change the 1st one to fixed duration & units/time then do a fill down for that column.

2. go to the project directory make sure that your porject is highlighted click on calculations then in the lower left make sure that 

reset remaining duration and units to original