How to determine activities without predecessors or successor

3 replies [Last post]
Binh Vu
User offline. Last seen 6 years 39 weeks ago. Offline
Joined: 13 May 2017
Posts: 4
Groups: None

Hello everyone,

Someone can help me, how to issue the report as below.
Thank you so much.

4984
untitled.png

Replies

Zoltan Palffy
User offline. Last seen 10 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

Tom is correct except that you have to first check the box thats says Log to file and give the log file a location to write to then you have to schedule the project then after that you can view the log file 

Binh Vu
User offline. Last seen 6 years 39 weeks ago. Offline
Joined: 13 May 2017
Posts: 4
Groups: None

Thank you so much.

Tom Boyle
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 28 Nov 2006
Posts: 304
Groups: None

In P6, F9. View Log.