Stacked Histogram across suite of Projects sorted by Role

3 replies [Last post]
Katherine Murphy
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 20 Jan 2017
Posts: 5
Groups: None

I have a suite of projects that is resource loaded with defined roles first and people filled in as resources once they are assigned.  I have a stacked histogram set up to show by resource and by role separately. Is there a way to combine that function in p6? I need to be able to choose a role and show that stacked histogram for say "engineers" and have the stack be bob, suzy, joe, fred, etc., excluding "project managers" and "designers", for instance.

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

first filter for the activities that have the people assigned that you are looking for then

view resource usage profile on the lower portin of the screen on the left hand side select the upside down triangle and select 

Select view then by role 

Katherine Murphy
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 20 Jan 2017
Posts: 5
Groups: None

I want to be able to filter out the role and see a stacked histogram of people within that role/discipline.

Right now, I can see stacked histogram by role or stacked histogram by resource but I can't figure out how to filter if I need a certain role broken out by only the people assigned there.

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

when you view the resource usage profle NO  NOT select the role but the resource name. In the left portion of the resource usage profile you can group and sort on resouce NOT ROLE