Stacked Histograms

2 replies [Last post]
Mark Porter
User offline. Last seen 10 weeks 2 days ago. Offline
Joined: 8 Aug 2007
Posts: 55
Groups: None
Using P3e I’d like to produce a stacked resource histogram displayed by each project. Currently I assign a resource accross multiple projects & would like to be able to see the cumalitive loading on a per project basis. I have been advised that this is possible but I can’t find a project filter to apply in my filtering option.

I am also having trouble naming & changing the X & Y axis information in the graphs.

Replies

Khuong Do
User offline. Last seen 16 years 31 weeks ago. Offline
Joined: 1 Sep 2006
Posts: 38
Groups: None
Hi Mark
You must use myPrimavera Resource portlet to produce this kind of report.
In Resource portlet choose Resource Analysis. On Chart Type choose Stacked Histogram.
Then choose the resource you want and it will show resource loading grouped by project.

Thanks
Khuong
Andrew Dick
User offline. Last seen 8 years 13 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Mark, this is very possible ith the My Primavera add on, I’m currently doing this in the assignments view with a spreadshet, as this is how my resource managers like to see things. I haven’t tried the stacked histos in the client, but will be very interested in further posts here.

Andy