importing resource assignment error

3 replies [Last post]
Rami Refaat
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 17 Aug 2011
Posts: 13
Groups: None

Dear All

im trying to import resource assignmenet to a project, resource is material im importing only the budget unit and im getting the below error any help or suggestion please.

ERROR: TBOBasedDataManager.InsertNewObject: Cannot resolve foreign key for TASKRSRC

 

Replies

Zoltan Palffy
User offline. Last seen 8 weeks 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

As Nihat Said do not change any order of the columns or format of the columns

you can not ADD a new resource if the resource does not already exist in the database

Nihat Yildirim
User offline. Last seen 3 years 15 weeks ago. Offline
Joined: 23 Nov 2001
Posts: 10
Groups: None

You might have wrong activity ID or resource IDs specified in the import file.

Also don't change the order of sheets in the XLS file.

Zoltan Palffy
User offline. Last seen 8 weeks 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

make sure that calculate costs from units is set to no. if it is not run a global change and chnage it to no. Also make sure that the resource exists