Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How can I see planned AND remaining work in the same report?

8 replies [Last post]
Alex Garcia
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

If I am running a cost loading report out of a status project, for the purposes to inform my customer what unfinished work is remaining on the project, and how it is time phased, I am only seeing BCWS.  The remaining work of the in progress activities doesn't show up on the report, so I am short on budget.

 

How can I get both planned and remaining to show up on the same report, with time phasing represented as it stands in the status project?

 

Thank you!

Replies

Johannes Vandenberg
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Alex

Try this,

> Go to the Activity Usage Spreadsheet

> Go to the Righthand bottom part of the bottom screen.

> Click right and select the following spreadsheet fields. Planned total cost, Remaining total cost and Actual total cost

Now, the values  are displayed in the spreadsheet.

Select, copy and paste in Excel.

Regards

 

Johannes

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

sometime this works if you want to dump this to excel go to Project the Resource Assignments

get your time frame on the rigth hand side (by monthor quarter or what ever) by right click and select timescale

then on the roll up your resource on the left hand side click the + sign 

Then on the right in the timescale select the first period that you want the data for and hold the shift key and select the last period that you and data for 

select edit then copy 

go to excel and select paste. 

Alex Garcia
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

Thank you!  And can this be dumped into Excel?  The end result is we need to submit the data to our financial people via Excel. 

Basically, we are required to submit our funding requirements via Excel to our CFO counterparts.  While our baseline is sound, the status project (or forecast, as many call it) is what is determining what scope is scheduled to occur within the given time frame.  With P6 cutting off the remaining work of in progress activities, my Excel numbers are short by that amount.

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

view show on bottom resource actviity uage profile and then right clikc on the right hand side in the histogram area and select Activity Usage Profile Options then Baseline and anything you want to comapre it to you can do this based on units or costs. You can also show a cumulative curve there as wel just chekc the box under cumulative.

Alex Garcia
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

I don't want the BCWS or Remaining work on in progress activities to show me the spread based on their baseline dates.  I want the budget spread out over the time period in which the status project says it is planned to take place.

Basically, our customer is asking us the question - "What does P6 state that we are planning to perform during a certain time period," and they want the answer in $, by financial period.  We initially ran a cost loading report out of the status project, but it only gave us the BCWS for the activities that had not yet started.  The activities that were in progress didn't show up at all.  The portion of the in progress activities that was claimed as BCWP didn't show up, which was perfect.  However, the remaining work also did not show up either, which meant our budget for the overall time period in question (Fiscal Year 17, for example) was short by the amount of the remaining work of the in progress activities.

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

not sure what you mean by phasing ?

Alex Garcia
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 21 Sep 2016
Posts: 9
Groups: None

I have the proper baseline attached and assigned.  I guess I didn't realize you could reference the baseline in a cost loading report.  I will look into that. Thank you!  Question:  Will it give me the time phasing of the in progress activities from the baseline or the status project?  I need the time phasing from the status.....

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

assign a baseline then reference it