Default activity start date

5 replies [Last post]
Vignesh S
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

I have create a new project on 18th Aug with start date as 01st Aug. But, while creating the activities the start date by default is getting picked as 18th aug which is the data date. I want project start date (01st Aug) as the default start date for all activities. Could anybody guide me on how to achieve it?.

Replies

Zoltan Palffy
User offline. Last seen 10 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

go to PROJECTS

highlight you project 

in the dates tab

set the start date and data date to august 1, 2016

Vignesh S
User offline. Last seen 8 years 32 weeks ago. Offline
Joined: 29 Apr 2015
Posts: 26
Groups: None

David Kelly, Thanks.... it worked

David Kelly
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

Schedule the project and pick a data date which is the default early start date

FERDINAND ANCHETA
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 18 Mar 2014
Posts: 6
Groups: None

constraint/actual the date, 01 Aug. alternatively, use as data date.

FERDINAND ANCHETA
User offline. Last seen 6 years 30 weeks ago. Offline
Joined: 18 Mar 2014
Posts: 6
Groups: None

constraint/actual the date, 01 Aug. alternatively, use as data date.