Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Dam Construction Schedule (Hydroelectric Power Plant)

2 replies [Last post]
naim gullu
User offline. Last seen 5 years 13 weeks ago. Offline
Joined: 3 Apr 2016
Posts: 2
Groups: None

Dear All,

I need your help if you can share with me a sample Schedule for Hydro-Electric power plant.

Kindly email it to naimgullu@gmail.com.

Thank you all and more power!

Best Regards,

Mehmet Naim Gullu

Replies

Mike Testro
User offline. Last seen 43 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Niam

The construction of an earth fill dam is a simple balance of the anticipated flow of the river and the speed that the dam can be constructed.

The biggest risk is overtopping which is where a flood will flow over the partly completed dam and wash it away.

There are two ways around this:

1. Complete river diversion through a relief chanel - best way but expensive.

2. Part river diversion through the turbine tunnel.

So stage 1 is the completion of the diversion and construction of the haul roads.

You may need a grout curtain through the river bed cracks so this will need a temporary coffer dam.

Stage 2 is getting enough haul units to carry both the clay infill and the earth embankments to build up the dam ahead of the rise in the river. Also make sure you have enough consolidation units at the dam to handle the incoming fill. You will need a colts foot roller for the clay core and vibrating rollers to compact the granular fill in the specified layers.

This is a crucial calculation and needs expert engineering input.

The higher up the dam the less earthfill is needed so it goes up quicker.

Start at the beginninbg of the dry season and consider using conveyor belts from the borrow sites.

Most contracts allow for the possibility of a 50 year flood as the employers risk.

When the dam has reached its top level then you place the riprap and construct the spillway.

The trubine hall can be started downstream when the dam is about halfway up when the risk of overtopping is reduced.

Installation of the turbines should coincide with the topping of the dam.

BTW a concrete dam will withstand an overtopping.

I trust that helps.

Best regards

Mike Testro

Mike Testro
User offline. Last seen 43 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Niam

Earthfill or Concrete?

Best regards

Mike T.