Importing resources and budgeted labor units from excel to P6 (2 diff programs)

6 replies [Last post]
Anas Khan
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 27 Jun 2012
Posts: 7
Groups: None

I have two programs.

1) original baseline.

2) substantial completion mep program.

What i have to do is, import resources and budgeted labor units from (2) to (1), but when i do this, it does not happen.

I think as they are two different programs, i will have to map the WBS(es) as well.

Can you help me out with this issue?

Replies

Zoltan Palffy
User offline. Last seen 1 day 12 min ago. Offline
Joined: 13 Jul 2009
Posts: 2592
Groups: None

no problem

Anas Khan
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 27 Jun 2012
Posts: 7
Groups: None

Thank you.

Anas Khan
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 27 Jun 2012
Posts: 7
Groups: None

Thank you.

Zoltan Palffy
User offline. Last seen 1 day 12 min ago. Offline
Joined: 13 Jul 2009
Posts: 2592
Groups: None

yes a straight copy will suffice then you can arrange the structure. When you copy it you have the option of copying the activities associated with the wbs or uncheck the activities option and just copy the wbs structure

Anas Khan
User offline. Last seen 1 year 41 weeks ago. Offline
Joined: 27 Jun 2012
Posts: 7
Groups: None
Thanks for the reply zoltan. The last step that u mentioned for wbs, just a direct copy past from one project to the otherwill suffice?
Zoltan Palffy
User offline. Last seen 1 day 12 min ago. Offline
Joined: 13 Jul 2009
Posts: 2592
Groups: None

1st make sure that in 1) that calculate costs from units is NOT checked if it it run a global change to uncheck it  

Then export the costs and unit information from 2) to excel then import the cost and unit information into 1). 

Make sure that during the export that you select resources and resource assignments also in the export in the columns for export make sure that you select resource name resource type budged labor units and budgeted labor costs.

Then import this into p6

for the wbs open both projects and copy the wbs from one project to another make sure that you are in the wbs directory when you copy the wbs