I have two programs.
1) original baseline.
2) substantial completion mep program.
What i have to do is, import resources and budgeted labor units from (2) to (1), but when i do this, it does not happen.
I think as they are two different programs, i will have to map the WBS(es) as well.
Can you help me out with this issue?